E.P.A. Issues Order to Implement Surface Fire Prevention Measures at West Lake Landfill and Finalizes Enforceable Schedule for Final Evaluation of Remedial Alternatives

Subscribe to our Hazardous Waste Environment News RSS Feed
Category: Hazardous Waste
Type: News
Source: EPA
Date: Thursday, December 10th, 2015



(Lenexa, Kan., Dec. 10, 2015) - The E.P.A. has issued a Unilateral Administrative Order (UAO) to Bridgeton Landfill, LLC; Rock Road Industries, Inc.; and Cotter Corporation to develop and implement surface fire prevention measures at the West Lake Landfill Superfund Location in Bridgeton, Mo. The order follows an Oct. 24 grass fire at the landfill.

Within 21 days of the effective date of the order, the parties must submit a surface fire prevention work project to E.P.A. that includes a project and schedule for:
  • Placement of non-combustible material as soon as possible over areas where radiologically impacted material (RIM) is currently known to be at or near the surface;
  • Targeted clearing of trees and brush with no cuttings extending below the soil surface in places where RIM is known to be located at or near the surface in Operable Unit-1 (OU-1), and the placement of non-combustible material over the cleared areas;
  • Testing to confirm that RIM located at or near the surface has been covered;
  • Air monitoring to ensure protection of on-site workers and the surrounding community during clearing of vegetation and placement of cover materials;
  • Maintenance of cover materials until E.P.A. chooses and implements a final remedy at the site.
"This E.P.A. order requires swift action by the parties to ensure that the risks of a surface fire, and the effects of any potential surface fire, are greatly reduced," said E.P.A. Region seven Administrator Mark Hague. "EPA will continue to use its authority at the Location to protect surrounding communities from any potential threats posed by the West Lake Landfill. Putting a stable cover over the RIM located at the surface is not the final remedy. It is a common-sense engineering control to address the challenge of surface fires until a final remedy is selected."

In addition to requiring surface fire prevention measures, the order requires the parties to submit within 14 days a framework for an Incident Management Project (IMP) at OU-1. Among other requirements, the IMP will:

  • Describe a system to allow for 24-hour Location observation;
  • Define responses for various emergency scenarios at OU-1, to include surface fires;
  • Include a staffing Project to ensure IMP implementation 24 hours a day, 7 days a week;
  • Identify when and how personnel will notify local emergency responders and regulatory authorities, to include EPA, the Missouri Department of Natural Resources, and the Missouri Department of Health and Senior Services in the event of any emergency scenario identified by the IMP;
  • Description of types of fire suppression measures;
  • Description of response measures to be taken after a surface fire event.
E.P.A. has also reached an arrangement with the parties on an enforceable schedule for evaluating remedial alternatives. This schedule requires specific actions throughout the next year so that E.P.A. can propose a final remedy to the public by the end of 2016.

A new report also released today concludes that soil samples taken at the location of the fire were consistent with naturally occurring background radiation readings.

The above referenced agreement, report, and the signed UAO are accessible on E.P.A. Region 7's West Lake Landfill website.

  User Comments  
There are currently no comments for this story. Be the first to add a comment!
Click here to add a comment about this story.
  Green Tips  
Fix a dripping faucet as soon as you can – even a slow drip can waste more than a gallon of water in a single day.
  Featured Report  
PCB Facility Reports
Find out the facilities in your state that have reported PCB activity

View Report >>

  Green Building  
Sustainable Building Advisor Program- The Next Great Step
Beyond LEED - check out The Sustainable Building Advisor Program....Read Complete Article >>

All Green Building Articles